Install the Air Handler / Coil
Mount level, build the drain + P-trap + float switch, and seal the plenum transitions.
Approx. 90 min
Before you start
- •Coil/air handler matches the condenser (AHRI) and the metering device (TXV/piston) is correct for the system.
- •Return/supply plenum and transitions sized to the unit's airflow (CFM) — undersized ducts starve the coil.
- •Drain route planned to an approved termination with the correct pitch; secondary drain or float switch path identified.
Tools & materials
Hanging strap / stand / brackets · Level · PVC pipe, primer, cement, P-trap fittings · Float / overflow switch · Mastic or UL-181 foil tape, sheet-metal screws