Install a Ductless Mini-Split
Mount the head level, core-drill a sloped/sleeved penetration, set the condenser, torque flares, N2 pressure-test, evacuate, then release the factory charge.
Approx. 300 min
Before you start
- •Head and condenser locations chosen: head with clear throw and condensate drainage, condenser with airflow clearance and a path for the line set.
- •Line-set length measured and compared to the maker's PRECHARGE limit (most units precharge for ~25 ft / 7.5 m); know the per-foot add and the precharge cap.
- •Correct breaker, disconnect, and 14/4 (or sized) connecting cable on hand; flare line set sized to the unit's ports (commonly 1/4 in liquid / 3/8 in or 1/2 in suction).
Tools & materials
Level + tape + stud finder · Core drill (2.5–3.5 in bit) + wall sleeve and sealant · Flaring tool (with ridgid/clutch-type yoke), tube cutter, deburr/reamer tool · Calibrated torque wrench(es) for flare nuts · Nitrogen + regulator, micron gauge, 2-stage vacuum pump, charging scale
View