Set a Packaged Rooftop Unit (RTU)
Rig/crane-lift with tag lines, seat on a level gasketed roof curb, flash and weatherproof, land duct/electrical/gas/condensate through the curb, verify 3-phase rotation, then start up.
Approx. 360 min
Before you start
- •Curb already set and flashed into the roof by the roofer, level within tolerance, and the curb matches the unit's supply/return opening layout (curb adapter if the new unit footprint differs from the old).
- •Rigging plan signed off: crane reach/capacity for the unit weight at the radius, roof structural load confirmed, lift path and landing zone cleared, weather (wind) acceptable for the pick.
- •Power, gas, and a condensate path to the roof are available; voltage/phase at the disconnect matches the nameplate (208/230 vs 460, single vs 3-phase).
Tools & materials
Crane + certified rigging (slings/spreader bar rated for the unit weight) and tag lines · 4-ft and torpedo levels, shims · Sheet-metal hand tools, self-tapping screws, duct sealant/mastic, foil tape (UL181) · Roofing-grade sealant / counter-flashing materials for weatherproofing · Manometer, combustion analyzer, clamp meter, phase-rotation meter