Split-System AC / Heat Pump Install

Whole-job check-off: pre-job, set equipment, line set, electrical, evac, charge, commission.

Approx. 420 min

Before you start

  • Matched AHRI system (condenser + coil/air handler) confirmed — mismatched coils void the rating and the warranty.
  • Correct refrigerant type for the equipment (R-410A vs R-454B/R-32) and a dedicated, clean gauge set/recovery tank for it.
  • Local permit pulled and load calc (Manual J) on file so equipment is sized to the house, not the old box.
  • Confirm electrical service has capacity for the new unit's MCA/MOCP before you start.

Tools & materials

Recovery machine + recovery tank (for changeouts) · Micron gauge + 2-stage vacuum pump · Nitrogen + regulator · Brazing kit or ProPress jaws · Digital manifold + accurate charging scale · Torque wrench, level, drill/impact · Multimeter + clamp meter

View

0% complete

Pre-job & permits

Set the condenser

Set air handler / coil

Line set

Electrical & controls

Evacuation & charge

Commission & handoff